Town and Village Beautification Team

Jon-Angus-and-Jessie.jpg

The Beautification Team are out and about, working hard to keep our town and village main streets looking beautiful. 

They work on everything from landscaping to repair works. Depending on the size of the job, they can spend anywhere between one to three weeks working in any area.

Council is asking the local community to assist us to identify areas that need extra maintenance by lodging a service request.

Town and Village Beautification Schedule 

Where

When

Details

Iluka

13 - 17 October

  • Beach access stairs completion

     

Grafton, See Park 13 - 17 October
  • Pressure washing and final paint touch ups
Grafton, Market Square 20 - 25 October
  • Painting and pressure washing
  • Prince Street tidy up
Wooli 27 - 31 October
  • Cenotaph handrail installation
  • Painting

 

Completed jobs 