Fixing Country Bridges

bridge building.jpg

Under the Fixing Country Bridges Program, we are replacing thirty-one bridges. This funding will allow for the construction of stronger, safer and more durable bridges within the Clarence Valley. 

We will be completing the works using both internal and external bridge contractors. Construction of some bridges is underway, whilst others will commence within the following 9 months.

In conjunction with Kyogle Council, we are conducting an Expression of Interest (EOI) tendering process for the following nine bridges via this link. We are calling for suitably qualified contractors for pre-registration of prospective tenderers. Applicants are initially evaluated against published selection criteria, and those who best meet the required criteria are invited to Tender (as tender type Pre-Qualified/Invited).

Applications close on 5 October 2021.

Wintervale Creek Bridge, Old Glen Innes Road

We are replacing the four span, two lane timber bridge with a two span, single lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Barretts Creek Bridge, Coaldale Road

We are replacing the three span, single lane timber bridge with a two span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Dundoo Floodway Bridge, Kungala Road

We are replacing the three span, two lane timber bridge with a two span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Winters Bridge, Jackadgery-Lillydale Road

We are replacing the two span, single lane timber bridge with a single span, single lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Billys Creek Bridge, Armidale Road

We are replacing the three span, two lane timber bridge with a three span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Coutts No 1 Bridge over Orara Floodway, Armidale Road

We are replacing a six span, two lane timber bridge with a four span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Coutts No 2 Bridge over Orara Floodway, Armidale Road

We are replacing the six span, two lane timber bridge with a four span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Koukandowie No 2 Bridge, Armidale Road

We are replacing the single span, two lane timber bridge with a single span, two lane concrete bridge.

A temporary side track bridge will be constructed to allow traffic to be diverted around the site during construction.

Skinners Swamp Bridge, Armidale Road

We are replacing the five span, two lane timber bridge with a three span, two lane concrete bridge.