Grafton Library Project

  • Project typeOpen Spaces & Facilities
  • Project scheduleLibrary will reopen early August
Grafton Library

Clarence Valley Council is pleased to announce the commencement of the highly anticipated repair works at Grafton Library. These works will restore this important community facility to its pre-storm condition and support the continued delivery of essential library services. While some temporary impacts such as noise and traffic disruptions may occur, these will be short-term and carefully managed through appropriate communication, planning and controls.

What’s happening?


At its April Council Meeting, Council resolved to award Tender RFT25/12 for the Grafton Library Project to Campbell Construction Co Pty Ltd.

The works are required to address significant building damage caused by a hailstorm and will return the facility to its pre-storm condition. The scope includes, but is not limited to:

  • Installation of a new roof
  • Replacement of the solar array system
  • Electrical repairs
  • Internal repairs and new finishes

When is it happening?


Preliminary works onsite are scheduled to commence on 19 June 2026.

Construction is expected to be completed within seven (7) weeks, weather and site conditions permitting.

Work hours:

  • Monday to Friday: 7:00 am – 5:00 pm
  • Weekends: Subject to additional approvals

Library service disruptions

Library undercover and rear parking will be disrupted from 19 June 2026 onwards.

The library carpark will be closed from 1 July – 7 July 2026. The library hub will be in operation with parking offsite and pedestrian access from 1 – 4 July.

The library (including hub) will be closed:

  • Tuesday 23 June 2026
  • Monday 6 – Sunday 11 July 2026

Background


Following a hailstorm in August 2025, the Grafton Library sustained significant roof damage, resulting in extensive water ingress and internal impacts.

Council has been working closely with its insurer to facilitate the restoration of the building. After completing detailed investigations and developing a comprehensive scope of works, a public tender was issued in January 2026 to engage a suitably qualified contractor.

Campbell Construction Co Pty Ltd was appointed in April 2026, and planning and approvals are currently underway ahead of construction commencing in mid-June.

What are the benefits?


This project will ensure the continued provision of regional library services to the community. In addition, the upgrades will:

  • Improve operational efficiency
  • Reduce ongoing maintenance costs
  • Enhance the overall sustainability of the facility

The project is funded by Council’s insurer; however, Council is required to initially fund the works and seek reimbursement upon completion.

Location

126-144 Pound Street, Grafton 2460  View Map

Google Map